Road Pavement Rehabilitation Projects

The Wire Road rehabilitation project in Zephyrhills is scheduled to begin the week of August 16, 2021. The road work will include road base rehabilitation and milling and resurfacing of the existing road, as well as new pavement markings and restriping.

The paving project includes Wire Road, from County Road 54 to Gall Boulevard (U.S. 301), in the north and southbound lanes.

Project Details:

  • Work hours are Monday through Friday, 9 a.m. to 4 p.m.
  • Expect single lane closures with message boards directing traffic.
  • Project is expected to take 32 days to complete, depending upon weather conditions.
  • Target completion date is October 29, 2021.

Asphalt Paving Systems (APS) is the contractor for this Pasco County Department of Public Works project. 


The Little Road Pavement Rehabilitation Project in New Port Richey is scheduled to begin the week of July 25, 2021. The road work will include milling and resurfacing of the existing roads, as well as new pavement markings and restriping.

The paving project includes northbound and southbound lanes on Little Road from SR 54 to Trinity Boulevard.

Project Details:

  • Work hours are Sunday through Thursday, 7 p.m. to 6 a.m.
  • Expect single lane closures with message boards directing traffic.
  • Project is expected to take 30 days to complete, depending upon weather conditions.
  • Target completion date is September 30, 2021.

Ajax Paving Industries of Florida is the contractor for this Pasco County Department of Public Works project.